Donnelley Constructions

Chatswood Willoughby Uniting Church

Client:  Uniting Church
Location:  Willoughby, BSW
Value:  $6,688,000
Start date:  24/10/2009
End date:  23/06/2010

Willoughby Uniting Church

Donnelley Constructions was contracted by the Uniting Church to demolish three redundant buildings, renovate two heritage listed buildings and construct a new Church complex at Willoughby.

This included a hall, kitchens, learning facilities, a meeting room, office space and a 26 space car park. A 240,000 litre tank was constructed as per DA requirement and stored recycled water to be reused, ensuring construction sustainability. A large glass atrium which cut into the roof of the existing Church allowed it to be visible as an entrance feature of the new facility.